|
VOLTAGE SENSING,
MEASUREMENT & PHASING
Abstract
Sensing of energized lines, accurate voltage measurement, and phasing by
portable isolated instrumentation has proved practical and reliable on
modern underground systems. Specifically designed solid state HV
voltmeters and accompanying test and verification devices have proved
useful and reliable in conjunction with the capacitance voltage test point
now found on many devices. Standardization on practical values of
capacitance and surface leakage on voltage test points is still a
consideration to achieve maximum usefulness.
| |
 |
|
| |
Figure 1: Typical
voltage test point; C1 HV end capacitance; C2
LV end capacitance |
|
Underground systems with shielded
cables and connectors provided few points for direct hot line measurement.
This presents considerable difficulty in determining the presence of
voltage on an energized line and even more difficulty in accurate voltage
measurement and phasing with a portable voltmeter. Considerable help has
had been provided by the voltage test point, a capacitance type voltage
tap now being used in several types of cable connectors, elbows, splices,
and equipment. This type of tap is essentially a capacitive voltage
divider which makes use of the cable's, connector's, or bushing's high
voltage insulation between the HV conductor and a conductive, isolated,
plate or band to create a useful HV capacitor under the outer shield (see
Figure 1).
Capacitance Ratios
In many of the cable terminations now being used, the HV capacitance of
the voltage test point between the HV conductor and the isolated tap plate
is in the order of 1.6 to 1.8 picofarad (C1 of Fig. 1). This value is
obtained by choosing the proper size of a pickup plate or band, its
distance from the HV conductor, and the arrangement of shielding in the
molded connector or equipment.
Accompanying this HV capacitance is low voltage capacitance in the order
of 6 to 8 picofarads to ground (to shield) (C2 of Fig.1), thus creating a
combination of two capacitances giving a voltage divider effect. These
values give a basic average ratio of (7+1.7) / (1.7) or (8.7) / (1.7)
which reduces to approximately (5.1) / (1). Larger values of the LV
capacitance could also be used as a standard. For a 10 to 1 ratio
approximately 15.75PF would be necessary, or it can be even larger. The
low voltage end capacitance is not critical if the HV end is standard.
Voltmeter impedances can be low enough to "swamp out" a 6 to even a 50PF
capacitance, the voltmeter itself then establishing its own ratio
independent of the LV end capacitance.
The voltmeter impedance must be kept very high, to more easily match the
variations in the HV end and the overall ratio is then mostly dependent on
the capacitance ratio, then this LV end capacitance also becomes critical
in establishing the ratio.
Design Considerations
In the design of the capacitances of the voltage test point, shielding
positions as well as sizes of conductors, and thickness, dielectric
constant and operating temperature of the dielectric must be considered.
Capacitance variation, with variation in applied voltage level, can also
be a consideration.
In order to obtain the desired HV end capacitances, the size of the pickup
plate, which is generally at a required distance from the conductor due to
required insulation level, is the major variable available. This plate can
be enlarged to a band around the entire conductor insulation, since the
size of the HV conductor plays a critical part in determining the
capacitance.
In the plug-in cable connectors, if internal grading shields are not
shaped properly to shield the tap plate from the cable conductor,
variations in size of cable conductor and dielectric constant of cable
insulation will appreciably change the HV end capacitance to the tap
plate.
One utility found it could even determine the size of a conductor by the
voltage reading. The larger the cable conductor, the higher the voltage
reading with the same style of elbow connector and a fixed line voltage.
Some brands show considerably more variations due to conductor size
variation since the plate is not as remote from the incoming cable.
A major design consideration of a voltage test point also is the external
insulation path to ground. Some present designs have extremely short paths
for an area that should maintain over 1,000 megohms leakage resistance if
a very high input impedance voltmeter is used. A long skirted path is
desirable. On one of the widely used elbows, the voltage output of the
test point unloaded is 1/5 of the 7.2KV line to ground voltage, or
approximately 1.4KV for a 12.5KV system. This, of course, is so limited in
current output (5 to 10 microamps) by the low source capacitance that it
in itself is not dangerous, but it can cause leakage paths to form on the
short insulation path if cleanliness is not constantly observed.
Some brands and models of taps have somewhat different capacitances and
therefore somewhat different ratios, some varying as much as 2 or 3 times
these amounts. This creates considerable difficulty in designing a
universal voltmeter to use these taps and an effort is being made to
standardize on at least the most important, the HV end capacitance in the
order of 1.75 picofarad. The low voltage end capacitance is less
important; however, it has been suggested that it be standardized in the
value of 7PF to give a basic minimum ration of 5 to 1, which then can be
padded externally to give any higher ratios desired.
A much higher HV end capacitance would be considerably better, perhaps in
the order of 3PF or even 10 or 15PF, since the very low value of 1.75PF
presents considerable difficulty for accurate voltage measurement with an
economical device. The higher capacitance would also reduce the effect of
moisture or dirt which could cause low or even zero readings if the test
point were not cleaned properly. However, it appears that increasing this
HV capacitance involves changing present production molds and adds
considerable development expense to the connectors. Thus it may be
economically unfeasible for an established item to be modified to meet the
desired value.
Sensing Energized Lines
Using this capacitance voltage tap, or voltage test point as has been
suggested for a standard name, for merely indicating an energized line is
relatively easily done with a moderately priced high impedance sensing and
indicating device. Using it for accurately measuring actual voltages line
to ground is more difficult because of meter loading and external
interference. Further, using it for line to line voltage measurement and
phasing becomes even more difficult with added external capacitance
problems. However, with proper matching impedance, input voltages, and
shielding in an objectively designed high impedance voltmeter, all of
these measurements can be made generally within better than 10%, usually
better than 5%, depending primarily on the accuracy of the voltage test
point capacitances themselves.
At this time there are different capacitances in some manufacturers’
models. For accurate measurement the voltmeter then must have different
input matching and ratios for voltage test points on some of the different
brands and types of connectors and equipment.
| |
 |
|
| |
Figure
2: Portable Hi-Z HV Voltmeter and accessories for measuring line to
ground, line to line, and phasing voltages from capacitance voltage
test points and direct HV line. |
|
Portable HV Voltmeter
A solid state portable voltmeter and associated accessories, called the
Hi-Z® HV Voltmeter (see Figure 2), has been developed for hot stick use by
Ross Engineering Corporation to match the voltage test point on the
Elastimold 15KV elbow. It also matches the Burndy 15KV load break elbow
test point, the ITT Blackburn elbow test point and others, without need
for changing voltmeter probes, but will also match the brands and models
with different capacitances in their test points by changing either the
voltmeter's removable probe or a selector switch. Experience with
production units in the field for the past three years has shown this
method is reliable for portable voltage and phasing measurement.
With such an extremely high impedance source (1.75 picofarad is
approximately 1,500 megohms 7PF is approximately 370 megohms at 60Hz)
extreme care must be taken in shielding the higher impedance (100-1000
megohm) pickup probes and voltage test points, particularly if exposed HV
taps or lines are near the test point. External pickup is not nearly as
critical when using the 1 megohm to 85 megohm probes which can be used
with specific brands of connectors or equipment.
Phasing
For line to line phasing by use of test points, capacitance loading must
be carefully balanced to prevent pickup or unequal changes in capacitance
ratios, which could cause serious errors in line to line or phasing
differential readings.
The voltmeter is provided with both line to ground (Figure 3) and line to
line and phasing probes (Figure 4) which are shielded and balanced for
accurate measurement by voltage test points for lines from a few volts to
25KV, as a line to ground, a line to line, or a phase differential
voltage.
 |
 |
| Figure 3: Application of Voltmeter Probe for line to ground voltage
measurement on voltage test point. |
Figure
4: Application of Voltmeter Probes for phasing or line to line
measurement on voltage test points. |
This has increased its versatility
considerably, since it also can detect the presence of AC voltage, even at
the surface of many semi-conductive shielded concentric neutral cables,
thus indicating voltage existing on the internal conductor when there is
no voltage test point available. Due to the variations in semi-conductive
shielding resistance in various brands of cables, not all cables will
indicate properly. If voltage presence is indicated, the cable is
definitely energized. However, for some types of semi-conductive shielded
cables with very low or very high surface resistance, or for metallic
shielded cables, insufficient indication may result.
Contamination Sensing
Since most voltage test points have such high impedence, they can be
subject to leakage contamination if care is not taken to keep the tap
clean and dry while making a test. Usually a protective grounding cap is
provided and silicone grease is liberally applied to the external
insulating portion of the tap. Leakage resistance in the order of 1,000
megohms (in some types 100 megohms) or less can seriously effect the
voltage test point calibration. Leakage resistance under 20 megohms on a
voltage test point can indicate practically zero reading when using the
higher impedance voltmeters.
A voltmeter supplied with a combination AC voltmeter tester-verifier and
DC leakage current-megohmmeter, provides both 400V AC for testing the
voltmeter before and after a measurement, and 500V DC for measuring the
leakage resistance of the voltage test point or any other HV insulation in
the range of 20 megohms to 2,000 megohms. This leakage or contamination
testing unit for verifying voltage test points is designed for portable
hotstick use. While the standard unit is rated for 600V maximum, some
models can safely contact an energized HV line directly. They can also
measure insulation leakage resistance at 500V DC to 2000 megohms, or
0-15KV DC or 0-36KV DC for higher voltage insulation to 30,000,000 megohms,
even with the presence of up to 15,000V AC, if the 85 megohm or higher HV
probe is used as a limiting resistance.
Conclusion
With the increased use of capacitive voltage test points, sensing of
energized lines and accurate voltage measurements and phasing has been
shown to be practical and desirable for underground systems.
Test point capacitance values still leave much to be desired for
uniformity and greater reliability. One suggested method of standardizing
on only a ratio of HV to LV capacitance is considerably less desirable
than standardizing on a fixed value of HV end capacitance and also a
ratio, although a ratio is less critical.
The HV end capacitance should be established at as high a value as
practical to minimize contamination and external shielding problems.
Voltmeters with accessories have shown it is feasible and reliable to
safely and accurately measure voltages and phase on underground systems
with the capacitive voltage test point. Sufficient varieties of hotstick
designed measuring and testing devices now exist to obtain most HV
conductor information by use of portable isolated devices.
References
1. Proposed IEEE - NEMA Joint Standard for Separable Insulated Connectors
January, 1970
Sponsored by The Task Force on Switching and Overcurrent Protection,
Underground Distribution Subcommittee, IEEE Transmission and Distribution
Committee and
The Primary Connector Working Group, Technical Committee, Electrical
Connector Section, NEMA
Mr. Hugh C. Ross is President and Chief Engineer for Ross Engineering
Corporation. |